    Making Madagascar’s Heavy-Load Route Deliverable

    Operational consultancy for a 25 MW power project in Madagascar, 2018

    Operational Consultancy
    Sam Hardwick
    Lead Advisor
    Sam Hardwick

    Emeritus Advisor

    View Profile
    Key Outcome

    25 MW project logistics delivered on time and within budget.

    Executive Summary

    For a power project in Madagascar in 2018, cargo capacity was only part of the logistics challenge. The defining task was making the route from Tamatave Port to Antananarivo capable of supporting exceptionally heavy equipment. Restricted infrastructure, limited site access and heavy-load constraints threatened delivery before transport could begin.

    The delivery scope covered more than 500 containers, five transformers each exceeding 55 metric tonnes, and out-of-gauge cargo, sourced from over 12 origins. Across a 12-month planning period, the operation had to accommodate scope changes, limited sailing options and rate increases while maintaining a credible delivery budget.

    The decisive intervention was route enablement: extensive route engineering, major road improvements and strengthening three critical bridges, supported by government and stakeholder coordination. The reported outcome was completion against the project’s time and budget commitments, with clear cost and schedule visibility throughout.

    Key Metrics Grid

    500+

    Containers: 20ft, 40ft and 40ft high-cube

    5 × 55MT+

    Transformers, alongside out-of-gauge cargo

    12+

    Origins across multiple countries

    3

    Critical bridges strengthened

    The Challenge

    01 — A route that needed enabling

    The long inland journey from Tamatave to Antananarivo could not be treated as a routine container movement. Road conditions and bridge capacity required engineering intervention before heavy equipment could reach the destination.

    02 — Heavy loads and restricted access

    Five transformers exceeding 55 metric tonnes each, together with out-of-gauge equipment, created specialist transport requirements. Limited site access and handling capability meant the final delivery interface was as important as the inland route.

    03 — Multiple authorities and stakeholders

    Government approvals, permits and stakeholder negotiations were essential dependencies. Infrastructure work and heavy-load movements required alignment across parties whose decisions could affect both execution readiness and the delivery schedule.

    04 — A changing international supply picture

    Cargo from more than 12 origins had to move despite limited sailings and increasing rates. Scope changes continued throughout the 12-month planning period, placing pressure on transport arrangements, cost assumptions and delivery continuity.

    05 — Limited internal resources

    Planning accuracy was a critical success factor because internal resources were constrained. The client needed a credible, executable budget and clear visibility of changing cost and schedule exposure—not simply an initial freight estimate.

    The Approach

    The delivery approach connected planning, physical route readiness and multi-party execution rather than treating them as separate workstreams.

    Phase 01 — Build a deliverable plan

    Planning addressed the container mix, transformer weights, oversized cargo, multiple origins and destination restrictions. Establishing a credible budget at this stage was central to the engagement: transport decisions needed to reflect the actual infrastructure and handling constraints, not an assumed standard route.

    Phase 02 — Enable and control the route

    The delivery solution incorporated extensive route engineering, major road improvements and strengthening of three critical bridges. Sam and his team coordinated the route-enablement effort with relevant parties, linking physical readiness to transport requirements so the heavy-load corridor became executable.

    Phase 03 — Align approvals and specialist partners

    Government coordination, permits and stakeholder negotiation supported movement readiness. Local and international partners were coordinated around specialist transport, out-of-gauge cargo and restricted site access, connecting international shipping arrangements with the practical requirements of inland delivery.

    Phase 04 — Adapt while preserving visibility

    The delivery programme accommodated evolving scope, constrained sailings and rate increases over the planning period. Maintaining clear cost and schedule visibility helped the client understand changing conditions while Sam and the project partners sustained delivery continuity through execution.

    Results & Impact

    500+ containers delivered

    The containerised scope reached its destination alongside five 55MT+ transformers and oversized equipment, demonstrating execution across both standard and specialist cargo requirements.

    3 critical bridges strengthened

    Bridge strengthening and road improvements addressed the infrastructure barriers that threatened heavy-load delivery. The route became a practical delivery solution rather than an unresolved project dependency.

    On-time completion

    The reported delivery result protected the power project’s schedule despite lengthy inland transit, restricted access, limited sailing options and scope changes during planning.

    Within-budget delivery

    Cost control was maintained despite rate increases and evolving requirements. Clear cost and schedule visibility supported client assurance throughout a complex, multi-party operation.

    Conclusion

    The value of this engagement lay in making delivery possible before relying on transport execution. Route engineering, infrastructure improvements and stakeholder alignment converted a high-risk corridor into an executable logistics solution, supporting the reported schedule and budget outcome.

    For future power and industrial projects facing similar constraints, the lesson is clear: treat route readiness, approvals, specialist handling and change management as one integrated delivery challenge. Early planning and sustained control will remain essential to keeping projects moving.

    Plan | Control | Deliver